Hall Renovations

The Hall committee are working on renovating the Hall. Substancial funding has been made available for this work by Kingoldrum Landward West Community Grant Scheme, KLWCGS.

Work completed

  • Repairs to the roof including refitting valleys between porch and hall and sealing gap between tin and slate roof [2022]
  • Repair rotten timber in porch and other timber repairs [2002]
  • Repointing of all external stonework [2023]
  • Replace main hall ceiling (and new insulation in roof)
  • Replace rotten Kitchen window [2024]

Work planned

  • Refit kitchen [2023/24] - see below

Kitchen refit Jan / Feb

We are having the kitchen refurbished. The new units have been delivered and the old unit taken out. Unfortunately we have found a significant damp and structural problems which needs to be dealt with before the refit work can continue. The kitchen may be out of action for longer than planned, and the new units and kitchen contents are currently stored in the main hall. This restricts events that can be held in the Hall.